Volt Rise Calculation

Tuesday, October 6, 2020
Training
by
Veli Markovic

What is volt rise?

The voltage on the grid varies throughout the day depending on how much power is being drawn from the grid and much solar is being exported. For energy to flow, the voltage at the inverter must be higher than at the grid. Issues can occur when cables haven’t been sized correctly because too much resistance results in a rise in voltage which can result in self-protection methods being instigated.

How much can it rise?

In AS/NZ 4777.1 volt rise is restricted to a maximum of 2% and this is from the Point of Supply (P.O.S.) to the last inverter with the highest current rating.

As the distributor requires this information, the installer must assess the existing cable and perform the necessary calculations. This determines any new cabling specs.


How much is this?

If we are talking 3 phase supply, we use a nominal voltage of 400V x 2% so we have 8 volts to play with over the entire cable run; both existing and planned.


Case study: Volt rise in a 100kVA system

We will assume a 100 kVA solar system on the AC side using 4 x 25 kVA inverters so will need to check that the cable from POS to MSB ( Main Switch Board) can carry the required current. Then a check of the volt rise along this section of the cable is required.


100 kVA system, step-by-step

In this particular example there are three sections of cable involved. The first is from the POS to the MSB; the next section is the run from the MSB to the PVDB secondary protection board; and then finally from the secondary protection board to the inverter with the highest current rating that is furthest away.

So:

  1. Check CCC (current carrying capacity of the cable then volt rise)
  2. Repeat for next run
  3. Repeat again for last run

What about the current?

We have 100 kVA of inverter capacity, a three phase system so the calculation is as follows:

  • 100 kVA/(1.73* x 400 Volts)
  • Looking at 144.51 Amps/phase
  • 1.73 is the square root of three because it is a three phase system


What existing cable is being used?

POS to MSB uses 95mm2 and the distance is 86 metres. Now AS/NZ 4777.1 refers to another standard, AS/NZ 3008 and specifically Table 7, Column 24 for example, see below:

 

  

All factors are important!

Same size cable can have different CCC* and this can depend on cable type, proximity to other cables, method and location of installation.

*current carrying capacity

You must make the assessment!

Table 7, Column 24 assumes a certain cable type installed in a certain way and this example is not the worst case scenario but is close. Ultimately it’s up to the installer to assess the cable situation themselves!

95mm2 cable can handle. . .?

According to the referenced AS/NZ 3008 table, (Table 7, Column 24) 95mm2 cable can carry 217 amps so all good in this respect but this is not all! We have to now look at the voltage rise so the next step is to go to another table that AS/NZ 4777.1 references, again in AS/NZ 3008, specifically, Table 41, column 6 which gives us a volt drop/rise factor of 0.449 for the existing 95mm2 cable. 

See table below:

(to the detectives out there - the factor described above is unchanged in AS/NZS 3008.1.1:2017!)


Now for the maths. . . . . .

So the calculation is  Vd/r = L x I x Vc/1000 where:

  • L   = cable run in metres, 86m
  • I   = the current, 144.51A
  • Vc = 0.449 mV/A.m

Vd/r = (86m  x  144.51A  x 0.449) /1000

Vr = 5.58 volts.

Voltage rise is 5.58 volts for POA to MSB and as a %, this is 1.39%, so from the MSB to inverters, the designer has 0.61% to play with or 2.42 volts!

How much work?

This process has to be repeated on all sections from POS all the way to the inverter(s)

How do you do this?

  • Basic maths and the ability to check the referenced tables involved
  • Write your own spreadsheet (VLOOKUP helps)
  • Find an existing spreadsheet online that has this functionality
  • Get outside help

Let’s continue

Let’s assume we have done the calculations from the MSB to PVDB  and  the cable selected there had a 0.86V rise in voltage so we add this figure to the existing volt rise: 

5.58V + 0.86V = 6.44V

So now we have a max of 1.54V left to play with for the PVDB to inverter run.

Final run to the inverters 

In our case we have 4 x 25 kVA inverters and they are all around the same distance from the PVDB, give or take a metre or so. Now, the voltage rise calculation is performed on the largest current output with the longest run so in this case we select one of the 25 kVA inverters that is furthest away. 


What formula do we use?

We could use the formula  25kVA / (1.73 x400) = 36 Amps for the 25 kVA inverters but best to check the data sheet for the max AC output of the inverter you are using and in this case we’ll roundup to 40 Amps. 

Cable selection, on we go

Say we select 10 mm2 and this can cope with up to 59A continuous according to AS3008 Table 7, row 24 and it’s only a 7 metre run.

7m x 40A x (3.86/1000) = 1.08 Volts

Total over the entire run is Vd = 7.52 Volts. A success seeing as we fall under the 8 volt maximum stipulated in the Standards.

Conclusion

Australian Standards stipulate a maximum 2% volt rise from POA to last inverter and your job is to calculate the volt rise and current carrying capacity for every section of cable run and also to take into account possible derating for heat due to installation location and method.

If you need any help with these calculations please contact our grid application service and one of our engineers will be happy to assist you.

About the author

Veli Markovic

CEC Designer
Veli has nearly two decades of experience in the renewable industry. He is passionate about providing people with valuable education and is highly regarded throughout the industry as an educator and operator.
Training videos

Every week we publish new videos and walkthroughs online.

More Posts

Related posts for you

Greenwoood nominated for CEC solar awards
Commercial
October 26, 2023

Greenwoood nominated for CEC solar awards

Commercial solar for a fish farm
Commercial
September 6, 2022

Commercial solar for a fish farm

Trentham solar & battery: revisited
Commercial
August 9, 2022

Trentham solar & battery: revisited

Ground Mount and Agrivoltaics
Commercial
July 26, 2022

Ground Mount and Agrivoltaics

Solar and batteries; life in the Mountains
Commercial
July 20, 2022

Solar and batteries; life in the Mountains

MC4 connections: how to crimp correctly
Training
June 1, 2022

MC4 connections: how to crimp correctly

Subscribe to our Youtube Channel for more videos